The fourth power unit of Zaporizhzhya NPP was inserted after the damage

Четвертый энергоблок Запорожской АЭС включили после повреждения

The power unit No. 4 of Zaporizhia NPP was connected to the grid after repairing the damage of the arrester phase “C” block of the transformer. This reports the press service of “Energoatom”.

Now under a set of power.

Just at the moment at the Zaporizhzhya NPP in the work are 3 units.

Comments on the operation of the main equipment of operating power units and staff there.

Continue the planned repairs of power units №1, №2, №3. Go 153 day overhaul of the unit 1, 95 day medium repairs of power unit No. 2 and 33 day overhaul of unit №3.

The radiation background at the industrial site and in sanitarno-protective zone (the area around the nuclear power plant radius 2.5 km) – 8-12 micro-roentgen per hour, which corresponds to natural radiation background at the location of the Zaporizhzhya NPP.

Related news: At Chernobyl began to export spent nuclear fuel from the first unit

Yesterday the generator of power unit No. 4 of Zaporizhia NPP was disconnected from the network under the action of electrical protection. Causes of tripping of protection are being investigated.

Source