At Khmelnitsky nuclear power plant had problems with both units
The radiation situation at the industrial site and adjacent area did not undergo changes.
Unit 2 of Khmelnitsky NPP is connected to the network after Troubleshooting. This was reported by the press service of the Khmelnytsky nuclear power plant on Friday, December 14.
“On 13 December at 22.30 unit 2 of Khmelnitsky NPP is connected to the network after the replacement of the transformer 2W excitation system of a turbogenerator”, - stated in the message.
As at 5.30 panicy reactor operates at nominal power. At power unit No. 1 of Khmelnitsky nuclear power plant went twentieth day of average planned repairs. The radiation situation at the industrial site and adjacent area has not changed, is at the level corresponding to the normal operation of power units and does not exceed natural background values.
We will remind, on December 13, 6.33 unit 2 of Khmelnitsky NPP was disconnected from power grid due to damage to the excitation transformer, phase V. This is the second problem on the unit, which is 13 November, was early connected after two months of repairs. On 17 November he was off to run vipranarayana of the turbine.
News from the Reporter.net Telegram. Subscribe to our channel https://t.me/korrespondentnet